![]() | RESOLUTION NO. 93 of 2020 DATED: May 26, 2020 |
RESOLUTION AUTHORIZING COUNTY EXECUTIVE TO SIGN AGREEMENT WITH LIRO ENGINEERS, INC. FOR ENGINEERING SERVICES-EXIT 29 REDEVELOPMENT PROJECT (ECONOMIC DEVELOPMENT AND PLANNING)
| Seconded by: | Pepe |
WHEREAS, the Village of Canajoharie and Montgomery County have an interest in revitalizing urban areas and stabilizing neighborhoods; and
WHEREAS, the Village of Canajoharie was awarded a total of $6,500,000 in Restore NY Communities grant funds for the purpose of revitalizing the Exit 29 site in which the County is owner to; and
WHEREAS, in order to carry out said tasks and goals associated with the awarded funds the County solicited RFQ 02-18 Engineering For Former Beech-Nut Plant Demolition/Rehabilitation and responses were received; and
WHEREAS, Resolution #153 of 2018 awarded the contract to LiRo Engineers, Inc. at a cost not to exceed $475,000 and Resolution #200 of 2019 amended the contract at cost not to exceed $560,000 for additional State Environmental Quality Review work on the western side; and
WHEREAS, additional work associated with the construction inspection, asbestos monitoring and demolition and design support for the western side of the site is necessary; and
WHEREAS, Part VI (C) (j) of the Montgomery County Procurement Policy allows to continue with professional services for existing projects that require the continuity of the professional services to ensure proper completion of the project.
RESOLVED, the Montgomery County Legislature hereby authorizes an amendment to the contract for a total cost not to exceed $725,000; and
FURTHER RESOLVED, that the County Executive, upon review and approval of the County Attorney, is hereby authorized and directed to sign the aforementioned contract.
RESOLUTION VOTE, passed with Aye(9). (5/26/2020)
I. Nature of Request:
Resolution authorizes the County Executive to sign an amended contract for Engineering services as it relates to the Exit 29 Redevelopment Project.
II. Justification:
Continued professional engineering services for this project are necessary.
III. Legislative Impact:
Pursuant to Section 3.02(g) of the Montgomery County Charter, the County Executive can make, sign and implement all contracts on behalf of the County within the authorized appropriations. Also authorized pursuant to the Montgomery County Procurement Policy.
IV. Financial Impact:
Resolution #120 of 2018 and Resolution #264 of 2019 authorized issuance of $6,000,000 in serial bonds for this project.
cc: | County Clerk County Treasurer |
|
|