![]() | RESOLUTION NO. 231 of 2018 DATED: October 23, 2018 |
RESOLUTION AUTHORIZING COUNTY EXECUTIVE TO EXECUTE CHANGE ORDER NO. 1 WITH LACORTE COMPANIES, INC. FOR FMCC CAMPUS LABS AND CLASSROOMS BUILDING PHASE I PROJECT
| Seconded by: | Pepe |
WHEREAS, Fulton and Montgomery Counties have approved a $1,000,000 FMCC Campus Labs and Classrooms Phase I Project, and
WHEREAS, funding will be from:
SUNY: | $500,000 |
FULTON COUNTY: | $250,000 |
MONTGOMERY COUNTY: | $250,000 |
and
WHEREAS, Resolution #69 of 2018 authorized the County Executive to execute certain Agreements for the FMCC Campus Labs and Classrooms Building Phase I Project, and
WHEREAS, one of these Agreements was with LaCorte Companies, Inc. in the amount of $99,111 to provide Electrical services, and
WHEREAS, the original contract agreement contained an $11,000.00 Contingency Allowance to be used for unexpected circumstances, and
WHEREAS, FMCC is recommending that LaCorte Companies, Inc.’s contract be decreased by $8,071.85 to credit back the unspent Contingency Allowance funds to the project.
NOW, THEREFORE BE IT RESOLVED, that the County Executive is hereby authorized and directed to execute Change Order No. 1 in the amount of (-) $8,071.85 with LaCorte Companies, Inc., and be it further
RESOLVED, that LaCorte Companies, Inc. revised contract amount will now be:
ORIGINAL CONTACT AMOUNT: | $99,111.00 |
CHANGE ORDER NO. 1: (-) | $8,071.85 |
REVISED CONTRACT AMOUNT: | $91,039.15 |
RESOLUTION VOTE, passed with Aye(8). Legislator Sweet was absent. (10/23/2018)
I. Nature of Request:
AUTHORIZING COUNTY EXECUTIVE TO EXECUTE CHANGE ORDER NO. 1 WITH LACORTE COMPANIES, INC. FOR FMCC CAMPUS LABS AND CLASSROOMS BUILDING PHASE I PROJECT
II. Justification:
FMCC is recommending that LaCorte Companies, Inc.’s contract be decreased by $8,071.85 to credit back the unspent Contingency Allowance funds to the project.
III. Legislative Impact:
The Montgomery County Legislature is authorized to pass this Resolution pursuant to Article 2 of the Montgomery County Charter.
IV. Financial Impact:
no financial impact - included in capital projects to college
cc: | County Clerk County Treasurer |
|
|