Montgomery County Seal!RESOLUTION NO. 231 of 2018
DATED: October 23, 2018
     

RESOLUTION AUTHORIZING COUNTY EXECUTIVE TO EXECUTE CHANGE ORDER NO. 1 WITH LACORTE COMPANIES, INC. FOR FMCC CAMPUS LABS AND CLASSROOMS BUILDING PHASE I PROJECT


Resolution by Legislator:   Sweet
Seconded by: Pepe

WHEREAS, Fulton and Montgomery Counties have approved a $1,000,000 FMCC Campus Labs and Classrooms Phase I Project, and 

WHEREAS, funding will be from:

SUNY:  $500,000
FULTON COUNTY: $250,000
MONTGOMERY COUNTY: $250,000

and

WHEREAS, Resolution #69 of 2018 authorized the County Executive to execute certain Agreements for the FMCC Campus Labs and Classrooms Building Phase I Project, and 

WHEREAS, one of these Agreements was with LaCorte Companies, Inc. in the amount of $99,111 to provide Electrical services, and 

WHEREAS, the original contract agreement contained an $11,000.00 Contingency Allowance to be used for unexpected circumstances, and 

WHEREAS, FMCC is recommending that LaCorte Companies, Inc.’s contract be decreased by $8,071.85 to credit back the unspent Contingency Allowance funds to the project. 

NOW, THEREFORE BE IT RESOLVED, that the County Executive is hereby authorized and directed to execute Change Order No. 1 in the amount of (-) $8,071.85 with LaCorte Companies, Inc., and be it further 

RESOLVED, that LaCorte Companies, Inc. revised contract amount will now be:

ORIGINAL CONTACT AMOUNT:  $99,111.00
CHANGE ORDER NO. 1: (-) $8,071.85
REVISED CONTRACT AMOUNT: $91,039.15

               

RESOLUTION VOTE, passed with Aye(8). Legislator Sweet was absent. (10/23/2018)


Statement of Legislative and Financial Impact:

I. Nature of Request:

AUTHORIZING COUNTY EXECUTIVE TO EXECUTE CHANGE ORDER NO. 1 WITH LACORTE COMPANIES, INC. FOR FMCC CAMPUS LABS AND CLASSROOMS BUILDING PHASE I PROJECT


II. Justification:

FMCC is recommending that LaCorte Companies, Inc.’s contract be decreased by $8,071.85 to credit back the unspent Contingency Allowance funds to the project.


III. Legislative Impact:

The Montgomery County Legislature is authorized to pass this Resolution  pursuant to Article 2 of the Montgomery County Charter.


IV. Financial Impact:

no financial impact - included in capital projects to college



cc: County Clerk
County Treasurer

Voting Record
Kelly (R) Yes 
Sweet (R) Absent 
Dimond (D) Yes 
Headwell, Jr. (R) Yes 
Wilson (R) Yes 
Duchessi (D) Yes 
Pepe (R) Yes 
Isabel (D) Yes 
Purtell (D) Yes 
     
STATE OF NEW YORK County of Montgomery ss.:

      This is to certify that I, the Undersigned, Clerk Of The Montgomery County Legislature, have compared the foregoing copy of resolution with the original resolution now on file in the office, and which was passed by the Montgomery County Legislature on the 23rd day of October, 2018, a majority of all the members elected to the Legislature voting in favor therof, and that the same is a correct and true transcript of such original resolution and of the whole thereof.
      IN WITNESS WHEREOF, I have set my hand and the official seal of the Montgomery County Legislature this 26th day of October, 2018


Totals:Aye: 8
Nay: 0 
Abstained: 0
Absent: 1



This resolution was approved by the County Executive on 10/26/2018
Resolution was enacted on 10/26/2018