![]() | RESOLUTION NO. 310 of 2008 DATED: October 28, 2008 |
| Seconded by: | Thayer |
WHEREAS, by resolution 63 of 2008, various contracts were authorized for the Classroom Building Renovation - Phase I - Mechanical System upgrade Project at FMCC, and
WHEREAS, by resolution 160 of 2008, various change orders with contractors were authorized for necessary items that were not in the original scope of work, and
WHEREAS, by resolution 225 of 2008 Change Order #2 with Four Strong Builders, Inc was authorized in the amount of $7,925 to provide for asbestos abatement not in the original scope of work and said change order has actually been completed at a total of $4,700, and
WHEREAS, it has been recommended that Change Order #2 be revised to reflect said change in pricing and it has also been recommended that since work is substantially complete, said contract be closed,
RESOLVED, that the Chairman of the Board of Supervisors, upon review and approval of the County Attorney, is hereby authorized and directed to sign a revised change order #2 with Four Strong Builders, Inc and also to close out said contract as follows:
Four Strong Builders
Original Contract Amount $243,000
Change Order #1 $ 14,500
Change Order #2 $ 4,700
________
$262,200
Total Paid to date $239,590
________
Balance Due(including retainage) $ 22,610
, and
FURTHER RESOLVED, that this resolution is contingent upon passage of a similar resolution by the Fulton County Board of Supervisors.
RESOLUTION ADOPTED with Aye(1819). Supervisor Walters was absent. (10/28/2008)