![]() | RESOLUTION NO. 64 of 2006 DATED: February 28, 2006 |
| Seconded by: | Cechnicki |
WHEREAS, by Resolution 251 of 2005, the Chairman of the Board of Supervisors was authorized and directed to sign an agreement with Stilsing Electric for the provision of services associated with the Integrated Campus Fire Alarm System Capital Project at Fulton-Montgomery Community College, and
WHEREAS, the Fulton County Planning Director and Project Design Engineer have recommended three changes proposed by Stilsing Electric in relation to said project, and
WHEREAS, Stilsing Electric has submitted estimates to complete said work,
RESOLVED, that the Chairman of the Board, upon review and approval of the County Attorney, is hereby authorized and directed to sign the following change orders with Stilsing Electric:
Original Contract Amount $ 240,570.00
Change Order No. 1 - Addition of Audio/Visual Devices $ 4,706.00
Change Order No. 2 - Corrections to the 2nd Floor Classroom $ 4,520.00
Change Order No. 3 - Corrections to the 1st Floor Classroom $ 3,222.00
____________
Revised Contract Amount $ 253,018.00
FURTHER RESOLVED, that this Resolution is contingent upon passage of a similar Resolution by the Fulton County Board of Supervisors
RESOLUTION ADOPTED with Aye(1593). Supervisor Dybas voted Nay. Supervisor Schumann was absent. (2/28/2006)
County Attorney |
cc: | County Clerk County Treasurer FMCC Fulton County Board of Supervisors Fulton County Planning |
|
|