TO: | Education/Government Committee |
Michael J. Pepe, Chair, Legislator, District 7 Martin P. Kelly, Legislator, District 1 Brian D. Sweet, Legislator, District 2 Herbert T. Allen, Legislator, District 3 Robert Headwell, Jr., Legislator, District 4 Daniel P. Wilson, Legislator, District 5 Chad J. Majewski, Legislator, District 6 Maria Kowalczyk, Legislator, District 8 - VACANT, Legislator, District 9 | |
FROM: | Patricia J. Beck, Clerk of the Legislature |
CC: | Legislators, County Attorney, County Treasurer |
DATE: | 10/15/2024 |
RE: | Committee Meetings |
Chair Michael Pepe has called a meeting of the Education/Government Committee for 6:05 PM on Tuesday, August 20, 2024 in the Legislative Chambers, Montgomery County Office Bldg, 64 Broadway, Fonda, NY.
Minutes of the meeting will be later posted on the Montgomery County website at www.co.montgomery.ny.us
Items on the agenda, at this time, are as follows:
1. (DISCUSSION)
A. Privilege of Committee Chair, Committee Members & Legislators to discuss items of interest, etc., regarding departments governed by this Committee
2. RESOLUTION AUTHORIZING COUNTY EXECUTIVE TO ENTER INTO A CONTRACT WITH SAHL'S GLASS AND GLAZING (LEGISLATURE)
3. RESOLUTION AMENDING 2024 OPERATING BUDGET (COUNTY ATTORNEY)
4. RESOLUTION AUTHORIZING COUNTY EXECUTIVE TO EXECUTE AN AMENDED CONTRACT WITH C.T. MALE FOR FMCC PAVING PHASE I ENGINEERING SERVICES (FMCC)
5. RESOLUTION AUTHORIZING COUNTY EXECUTIVE TO EXECUTE A CONTRACT WITH JMZ ARCHITECTS AND PLANNERS FOR FMCC WELCOME CENTER ELECTRICAL DISTRIBUTION PROJECT (FMCC)
6. RESOLUTION AUTHORIZING COUNTY EXECUTIVE TO EXECUTE A CONTRACT WITH CARVER CONSTRUCTION CO. FOR THE FMCC PAVING PRIORITY I PROJECT (FMCC)
7. RESOLUTION APPROVING 2025 CAPITAL PROJECTS (FMCC)
8. RESOLUTION ADOPTING 2024-2025 FMCC OPERATING BUDGET AND RESCINDING RESOLUTION 194 OF 2024 (FMCC)
9. OTHER
Res. # | Sponsor/Second | Recommendation | |
210 | RESOLUTION AUTHORIZING COUNTY EXECUTIVE TO ENTER INTO A CONTRACT WITH SAHL'S GLASS AND GLAZING (LEGISLATURE) | Pepe/Kowalczyk | Move to Full Legislature |
211 | RESOLUTION AMENDING 2024 OPERATING BUDGET (COUNTY ATTORNEY) | Kowalczyk/Wilson | Move to Full Legislature |
212 | RESOLUTION AUTHORIZING COUNTY EXECUTIVE TO EXECUTE AN AMENDED CONTRACT WITH C.T. MALE FOR FMCC PAVING PHASE I ENGINEERING SERVICES (FMCC) | Pepe/Sweet | Move to Full Legislature |
213 | RESOLUTION AUTHORIZING COUNTY EXECUTIVE TO EXECUTE A CONTRACT WITH JMZ ARCHITECTS AND PLANNERS FOR FMCC WELCOME CENTER ELECTRICAL DISTRIBUTION PROJECT (FMCC) | Kowalczyk/Majewski | Move to Full Legislature |
214 | RESOLUTION AUTHORIZING COUNTY EXECUTIVE TO EXECUTE A CONTRACT WITH CARVER CONSTRUCTION CO. FOR THE FMCC PAVING PRIORITY I PROJECT (FMCC) | Pepe/Wilson | Move to Full Legislature |
215 | RESOLUTION APPROVING 2025 CAPITAL PROJECTS (FMCC) | Pepe/Sweet | Move to Full Legislature |
216 | RESOLUTION ADOPTING 2024-2025 FMCC OPERATING BUDGET AND RESCINDING RESOLUTION 194 OF 2024 (FMCC) | Pepe/Sweet | Move to Full Legislature |
220 | RESOLUTION AUTHORIZING A FIREWORKS DISPLAY AT THE FORMER BEECH-NUT FACILITY (COUNTY LEGISLATURE) | Wilson/Pepe | Did Not Go Through Committee |
RESOLUTION NO. 210 of 2024 DATED: August 27, 2024 RECOMMENDATION: |
RESOLUTION AUTHORIZING COUNTY EXECUTIVE TO ENTER INTO A CONTRACT WITH SAHL'S GLASS AND GLAZING (LEGISLATURE)
|
|
WHEREAS, a bid was solicited for installation of new windows at the County Annex building via RFP 01-24; and
WHEREAS, this bid was awarded to Sahls' Glass and Glazing; and
WHEREAS, more funds are available to continue the window installation project.
NOW THEREFORE BE IT RESOLVED, that the Montgomery County Executive is authorized to enter into an amendment to the contract with Sahl's Glass and Glazing to increase the contract to $121, 300 and for additional amendments if funds become available. At a total contract amount not to exceed 350K.
RESOLUTION VOTE, passed with Aye(7). Legislators Allen was absent and District 9 VACANT.(8/27/2024)
I. Nature of Request:
RESOLUTION AUTHORIZING COUNTY EXECUTIVE TO ENTER INTO A CONTRACT WIHT SAHL'S GLASS AND GLAZING
II. Justification:
To continue installation of windows at the annex building as funds become available.
III. Legislative Impact:
Authorized pursuant to Article 2 of the Montgomery County Charter.
IV. Financial Impact:
No budget amendment is necessary.
cc: | County Clerk County Treasurer |
RESOLUTION NO. 211 of 2024 DATED: August 27, 2024 RECOMMENDATION: |
RESOLUTION AMENDING 2024 OPERATING BUDGET (COUNTY ATTORNEY)
|
|
WHEREAS, it is necessary to establish a new line to pay for expenses if the need arises for outside counsel; and
WHEREAS, County Law 501 authorizes the County Attorney to pay for these expenses when necessary and authorized by law.
THEREFORE BE IT RESOLVED,
TRANSFER FROM
A599 Appropriated Fund Balance $15,000
TRANSFER TO
1420 .00. 4431 Professional Services $15,000
RESOLUTION VOTE, passed with Aye(7). Legislators Allen was absent and District 9 VACANT.(8/27/2024)
I. Nature of Request:
RESOLUTION AMENDING 2024 OPERATING BUDGET
II. Justification:
It is necessary to have funds available to the office of the County Attorney.
III. Legislative Impact:
Authorized pursuant to County Law 501 and Article 2 of the Montgomery County Charter.
IV. Financial Impact:
One time deduction from fund balance.
cc: | County Clerk County Treasurer |
RESOLUTION NO. 212 of 2024 DATED: August 27, 2024 RECOMMENDATION: |
RESOLUTION AUTHORIZING COUNTY EXECUTIVE TO EXECUTE AN AMENDED CONTRACT WITH C.T. MALE FOR FMCC PAVING PHASE I ENGINEERING SERVICES (FMCC)
|
|
WHEREAS, Resolution 175 of 2023 authorized the Campus Paving Project Phase I and Resolution 57 of 2024 authorized a contract with C.T. Male for Engineering Services at Fulton Montgomery Community College; and
WHEREAS, the amended contract will include bid phase services, construction administration and observation; and
WHEREAS, FMCC received an updated cost proposal from C.T. Male Associates dated July 26, 2024 to perform these services at a cost of $62,900.00, and
WHEREAS, the contract breakdown of costs are as follows:
NYS | $31,400 |
Montgomery County | $15,725.00 |
Fulton County | $15,725.00 |
Total | $62,900.00; and |
RESOLVED, the Montgomery County Executive, upon review and approval by the County Attorney, is authorized and directed to sign a contract with C.T. Male Associates for engineering professional services at a cost not to exceed $62,900; and
FURTHER RESOLVED, that this resolution is contingent upon a similar resolution being passed by Fulton County.
RESOLUTION VOTE, passed with Aye(7). Legislators Allen was absent and District 9 VACANT.(8/27/2024)
I. Nature of Request:
Capital Project
II. Justification:
Services necessary for the FMCC Paving Project Phase 1.
III. Legislative Impact:
Authorized pursuant to Article 2 of the Charter.
IV. Financial Impact:
Matching funds are required from Montgomery County that are part of the $250K allocated as part of Resolution #175 of 2023.
cc: | County Clerk County Treasurer |
RESOLUTION NO. 213 of 2024 DATED: August 27, 2024 RECOMMENDATION: |
RESOLUTION AUTHORIZING COUNTY EXECUTIVE TO EXECUTE A CONTRACT WITH JMZ ARCHITECTS AND PLANNERS FOR FMCC WELCOME CENTER ELECTRICAL DISTRIBUTION PROJECT (FMCC)
|
|
WHEREAS, Resolution 175 of 2023 authorized the Welcome Center Electrical Distribution Project at Fulton Montgomery Community College; and
WHEREAS, the contract will include design, bid phase, and construction administration and services; and
WHEREAS, FMCC received an updated cost proposal from JMZ Architects and Planners dated July 30, 2024 to perform these services at a cost of $66,200.00, and
WHEREAS, the contract breakdown of costs are as follows:
NYS | $33,100.00 |
Montgomery County | $16,550.00 |
Fulton County | $16,550.00 |
Total | $66,200.00 |
RESOLVED, the Montgomery County Executive, upon review and approval by the County Attorney, is authorized and directed to sign a contract with JMZ Architects and Planners for professional services at a cost not to exceed $66,200; and
FURTHER RESOLVED, that this resolution is contingent upon a similar resolution being passed by Fulton County.
RESOLUTION VOTE, passed with Aye(7). Legislators Allen was absent and District 9 VACANT.(8/27/2024)
I. Nature of Request:
Capital Project
II. Justification:
Services necessary for the FMCC Welcome Center Electrical Distribution Project
III. Legislative Impact:
Authorized pursuant to Article 2 of the Montgomery County Charter.
IV. Financial Impact:
Matching funds are required from Montgomery County that are part of the $250K allocated as part of Resolution #175 of 2023.
cc: | County Clerk County Treasurer |
RESOLUTION NO. 214 of 2024 DATED: August 27, 2024 RECOMMENDATION: |
RESOLUTION AUTHORIZING COUNTY EXECUTIVE TO EXECUTE A CONTRACT WITH CARVER CONSTRUCTION CO. FOR THE FMCC PAVING PRIORITY I PROJECT (FMCC)
|
|
WHEREAS, Resolution 175 of 2023 authorized the Paving Priority I Project at Fulton Montgomery Community College; and
WHEREAS, after the advertisement of bids, six (6) bids were received.
CONTRACTOR | TOTAL BID |
Carver Construction Co. | $ 266,145.00 |
DelSignore Paving, Inc. | $ 274,907.2 |
Peter Luizzi & Bros. Contracting | $ 297,500.00 |
Wm. J. Keller & Sons Construction | $ 334,758.00 |
Birdsall Construction | $ 334,855.75 |
CFI Construction, Inc. | $ 335,755.50 ; and |
WHEREAS, The project engineers, CT Male, the Fulton County Planning Director, and Fulton-Montgomery Community College recommend awarding the contract to Carver Construction Co, 2170 River Road, PO BOX 890, Coeymans, New York 12045 who provided the lowest responsible bid in accordance with the specifications published July 2, 2024., and
WHEREAS, the contract breakdown of costs are as follows:
NYS | $133,072.50 |
Montgomery County | $66,536.25 |
Fulton County | $66,536.25 |
Total | $266,145.00; and |
RESOLVED, the Montgomery County Executive, upon review and approval by the County Attorney, is authorized and directed to sign a contract with Carver Construction at a cost not to exceed $266,145.00; and
FURTHER RESOLVED, that this resolution is contingent upon a similar resolution being passed by Fulton County.
RESOLUTION VOTE, passed with Aye(7). Legislators Allen was absent and District 9 VACANT.(8/27/2024)
I. Nature of Request:
Capital Project
II. Justification:
Services necessary for the FMCC Paving Priority I Project
III. Legislative Impact:
Authorized pursuant to Article 2 of the Montgomery County Charter.
IV. Financial Impact:
Matching funds are required from Montgomery County that are part of the $250K allocated as part of Resolution 175 of 2023.
cc: | County Clerk County Treasurer |
RESOLUTION NO. 215 of 2024 DATED: August 27, 2024 RECOMMENDATION: |
RESOLUTION APPROVING 2025 CAPITAL PROJECTS (FMCC)
|
|
WHEREAS, the Fulton Montgomery Community College Board of Trustees has recommended that the 2025 Capital Projects Request be undertaken at Fulton Montgomery Community College; and
WHEREAS, the project would involve the replacement of the Athletics Facilities Critical Maintenance, and Paving Priority 2; and
WHEREAS, the College proposes completion of said project utilizing monies from New York State 50% Match Funds, and the County Sponsors as follows:
NYS 50% Matching Funds | $473,244.50 |
Sponsor Match – Fulton | $236,622.25 |
Sponsor Match – Montgomery | $236,622.25 |
Total | $946,489.00 |
RESOLVED, that the Montgomery County Legislature hereby approves the 2025 FMCC Capital Projects at a cost not to exceed $946,489.00; and
FURTHER RESOLVED, that this project will require $236,622.25 of matching funds from Montgomery County; and
FURTHER RESOLVED, that this resolution is contingent upon passage of a similar resolution by the Fulton County Board of Supervisors.
RESOLUTION VOTE, passed with Aye(7). Legislators Allen was absent and District 9 VACANT.(8/27/2024)
I. Nature of Request:
Capital Project
II. Justification:
Athletics Facilities Critical Maintenance, Paving Priority 2
III. Legislative Impact:
Authorized pursuant to Article 2 of the Montgomery County Charter.
IV. Financial Impact:
$236,622.25 of matching funds are required from Montgomery County
cc: | County Clerk County Treasurer |
RESOLUTION NO. 216 of 2024 DATED: August 27, 2024 RECOMMENDATION: |
RESOLUTION ADOPTING 2024-2025 FMCC OPERATING BUDGET AND RESCINDING RESOLUTION 194 OF 2024 (FMCC)
|
|
WHEREAS, the Montgomery County Legislature adopted the proposed 2024-2025 FMCC Operating Budget by Resolution 194 of 2024; and
WHEREAS, Fulton County did not approve the proposed budget and it is necessary to pass a new resolution to pass the budget; and
WHEREAS, the Fulton-Montgomery Community College Board of Trustees has presented Fulton and Montgomery County, the sponsoring counties, with a 2024-2025 budget request, proposing a total FMCC budget of $15,385,889; and
WHEREAS, a public hearing related to the adoption of said FMCC Budget was held on July 23, 2024; and
WHEREAS, that the amount to be appropriated by the County of Montgomery, as its sponsor share of said Budget, shall be $ 1,645,821, which is 11% of the Operating Budget.
NOW, THEREFORE BE IT
RESOLVED, that Resolution 194 of 2024 is hereby rescinded ;and
FURTHER RESOLVED, that the Montgomery County Legislature hereby adopts the 2024-2025 FMCC Operating Budget ; and
FURTHER RESOLVED, that said sponsor’s share shall be included in the Montgomery County Operating Budget for 2025, as provided for in Section 6304 of the Education Law of the State of New York; and be it further
FURTHER RESOLVED, that this Resolution shall take effect upon adoption of a similar Resolution by the Fulton County Board of Supervisors
RESOLUTION VOTE, passed with Aye(7). Legislators Allen was absent and District 9 VACANT.(8/27/2024)
I. Nature of Request:
ADOPTING 2024-2025 FMCC OPERATING BUDGET
II. Justification:
The Fulton-Montgomery Community College Board of Trustees has presented Fulton and Montgomery County, the sponsoring counties, with a 2024-2025 budget request, proposing a total FMCC budget of $15,385,889.
III. Legislative Impact:
Pursuant to Article 2 of the Charter, the Montgomery County Legislature has the power to make appropriations.
IV. Financial Impact:
Montgomery County's sponsor share will be $1,645,821
cc: | County Clerk County Treasurer |
RESOLUTION NO. 220 of 2024 DATED: August 27, 2024 RECOMMENDATION: |
RESOLUTION AUTHORIZING A FIREWORKS DISPLAY AT THE FORMER BEECH-NUT FACILITY (COUNTY LEGISLATURE)
|
|
WHEREAS, Montgomery County has been approached with a request for permission to hold a fireworks display at the former Beech-Nut facility; and
WHEREAS, E29, the holder of the Purchase and Sale Agreement has agreed to this display as well; and
WHEREAS, Montgomery County supports the Village's efforts to promote economic development.
NOW THEREFORE BE IT RESOLVED, that the Montgomery County Legislature, upon the receipt of all necessary approvals and permits, signing of proper waivers and proof of proper insurance coverage in favor of Montgomery County, authorizes the use of the former Beech-Nut facility for a fireworks display on September 14, 2024 in the Village of Canajoharie; and
BE IT FURTHER RESOLVED, that the use of the former Beech-Nut facility for the fireworks display shall be at no cost to Montgomery County.
RESOLUTION VOTE, passed with Aye(7). Legislators Allen and VACANT were absent. (8/28/2024)
I. Nature of Request:
RESOLUTION AUTHORIZING A FIREWORKS DISPLAY AT THE FORMER BEECH-NUT FACILITY
II. Justification:
Montgomery County supports the Village's efforts to promote economic development
III. Legislative Impact:
Authorized pursuant to Article 2 of the Montgomery County Charter.
IV. Financial Impact:
No financial impact.
cc: | County Clerk County Treasurer |